QUEST A budget estimate should give the manager cost data accurate to within: 
A -5 to +10 percent of actual cost 
B -25 to +75 percent of actual cost 
C -30 to +75 percent of actual cost 
D -10 to +25 percent of actual cost 
E None of the above 
参考答案:D

QUEST The following types of costs are relevant to making a financial decision except: 
A opportunity costs 
B direct costs 
C sunk cost 
D unavoidable costs 
E None of the above 
参考答案:C

QUEST Which of the following types of cost are relevant to making financial decisions: 
A sunk cost 
B opportunity cost 
C material cost 
D A and C only 
E B and C only 
参考答案:E

QUEST In which of the following cost estimating techniques are statistics models used: 
A nonparametric cost estimating 
B parametric cost estimating 
C life cycle cost estimating 
D bottom-up estimating 
E All of the above. 
参考答案:B

QUEST Under the terms of 2/10 net 30, the buyer may: 
A deduct 10% of the invoice amount for payment within 30 days 
B deduct 2% of the invoice for payment within 10 days 
C incurs a penalty on 10% for payments more than 30 days late 
D settle the invoice with 2 equal payments; one within 10 days and the other within 30 days 
E None of the above 
参考答案:B