QUEST Using the situation stated in the Special window,  what is the cost variance for Case #9? 
A ¥-1,000 
B ¥1,000 
C -2000 
D 2000 
E 0 
参考答案:B

QUEST Using the situation stated in the Special window,  what is present value of $1000 at 12% at the end of 5 years? 
A ¥3,605.00 
B ¥0.57 
C ¥567.00 
D ¥892.86 
E ¥3.61 
参考答案:C

QUEST Using the situation stated in the Special window,  what is net present value of an annual income flow of $1600 at 14% over the next three years? 
A ¥3,713.60 
B ¥0.68 
C ¥1,080.00 
D ¥476.19 
E ¥2.32 
参考答案:A

QUEST Using the situation stated in the Special window,  what is the labor rate cost variance? 
A ¥5,500.00 
B ¥1,500.00 
C ¥-100.00 
D ¥-0.10 
E ¥5,600.00 
参考答案:D

QUEST Using the situation stated in the Special window,  what is the total price variance for direct material? 
A ¥140.00 
B ¥736.00 
C ¥0.02 
D ¥-350.00 
E ¥5,850.00 
参考答案:B