2010年PMP美国项目管理考试习题及答案四十二

发布时间:2010-02-25 共1页

QUEST Using the situation stated in the Special window,  what is the cost performance index for Case #9? 
A 1.1 
B 1.91 
C 0.83 
D 1.2 
E None of the above 
参考答案:A

QUEST Sunk costs are: 
A future costs held in reserve. 
B costs invested in commodities. 
C expended costs over which we have no control. 
D expended costs over which we have no more control 
E tax credits 
参考答案:D

QUEST Managerial Reserves are: 
A allowances to account for price changes that can occur over the life of a project. 
B incentive fees paid to managers for good performance. 
C funds used to offset poor cost or schedule estimates. 
D accounts to allocate and maintain funds for contingency programs 
E All of the above. 
参考答案:D

QUEST Life Cycle Costing: 
A is the concept of including all costs within the total life of a project. 
B is an activity devoted to optimizing cost/performance 
C is an activity of appraising the cost and technical performance of a completed project. 
D is a process of predicting the life of a project. 
E None of the above. 
参考答案:A

QUEST Using the situation stated in the Special window,  what is the schedule variance for Case #8? 
A 1000 
B 2000 
C -1000 
D -2000 
E 0 
参考答案:C

相关试题:

试题推荐:

百分百考试网 考试宝典

立即免费试用