2010年PMP美国项目管理考试习题及答案五十三

发布时间:2010-02-26 共1页

QUEST Using the situation stated in the Special window,   WBS Element Q is _____ budget by _____ percent. 
A Over, 16.66 
B Under, 16.66 
C Over, 10.0 
D Under, 10.0 
E None of the above. 
参考答案:A

QUEST Using the situation stated in the Special window,   the schedule performance index (SPI) for WBS Element P is: 
A 1.1 
B 0.9 
C 0.956 
D 1.15 
E 0.869 
参考答案:A

QUEST Using the situation stated in the Special window,   the cost performance index (CPI) for WBS Element R is: 
A 0.875 
B 1.14 
C 0.952 
D 0.833 
E 1.2 
参考答案:B

QUEST Using the situation stated in the Special window,  which WBS element has a favorable cost variance of $150? 
A Element P 
B Element Q 
C Element R 
D Element S 
E None of the above. 
参考答案:C

QUEST Using the situation stated in the Special window,  which WBS element is behind schedule but under budget? 
A Element P 
B Element Q 
C Element R 
D Element S 
E None of the above. 
参考答案:D