2010年PMP美国项目管理考试习题及答案五十一

发布时间:2010-02-26 共1页

QUEST The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget. 
A Unauditable. 
B Undistributed. 
C Preauthorized. 
D Contingency. 
E In-process. 
参考答案:B

QUEST Using the situation stated in the Special window,  what is the total fixed costs for manufacturing the widgets? 
A ¥3,000 
B ¥27,000 
C ¥27,270 
D ¥1,335 
E ¥1,000 
参考答案:E

QUEST Using the situation stated in the Special window,  the labor rate cost variance is: 
A ¥66,927 
B ¥68,329 
C ¥386 
D ¥-0 
E ¥18.36 
参考答案:D

QUEST In project-driven companies, costs are usually billed againest the project based upon: 
A The burdened labor rate of the actual employees who performed the work. 
B The burdened labor rate of the line organization average salary. 
C The burdened labor rate of the company  average salary. 
D The burdened labor rate of the average salary of the project team members. 
E None of the above. 
参考答案:A

QUEST The most common method for pricing out non-burdened labor hours for a three year project would be to: 
A Price out the hours at the actual salary of the people to be assigned. 
B Price out the work using a company-wide average labor rate. 
C Price out the work using a functional group average labor rate. 
D All of the above. 
E A and B only. 
参考答案:C