QUEST Which of the following is considered a direct cost for producing a widget? 
A The cost of the materials used to produce a widget. 
B The labor costs of the workers who actually produced the widget. 
C The rent for the building in which the widget was manufactured 
D The salary of senior management and the project sponsor 
E A and B only 
参考答案:E

QUEST The reason that cost management is so difficult in project management is that: 
A Projects by definition and nature are non-recurring events and are therefore difficult to predict. 
B There are no tools for identifying project tasks. 
C Project managers do not care about tracking costs, as only schedules are important to all project managers. 
D A and B only 
E B and C only 
参考答案:A

QUEST Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are referred to as the: 
A Baseline costs 
B Budgeted costs. 
C Estimates upon completion costs 
D Scheduled costs 
E None of the above 
参考答案:A

QUEST The difference between the BCWS and the BCWP is referred to as the: 
A Schedule variance 
B Cost variance. 
C Estimate of completion 
D Actual cost of the work performed 
E None of the above 
参考答案:A

QUEST When a project manager is running over the budgeted costs, the project manager can typically _____ to attempt to get the project back on budget. 
A Reduce features and/or functionality 
B Increase risk. 
C Incur a schedule slippage (to obtain more favorable pricing due to lengthened delivery times) 
D All of the above. 
E A and B only 
参考答案:D