QUEST The core function of the project manager is 
A Systems design 
B Client interfacing 
C Quality assurance 
D integration 
E参考答案:
参考答案:D

QUEST Situations calling for a matrix organization include outside pressure for dual focus,  _____ and pressure for high information processing capability. 
A Pressure for clear accountability 
B Pressure for reduced duplication of effort 
C Pressure for shared resources 
D Pressure for formalized communication 
E参考答案:
参考答案:C

QUEST Advantages of the functional (hierarchical) form of organization include  _____ and creation of technical competence. 
A Ease of horizontal coordination 
B Clearly defined authority 
C High information processing capability 
D Single voice to customers 
E参考答案:
参考答案:B

QUEST History has shown that project managers can be trained in a combination of ways.  Which method is usually preferred by most companies? 
A Experiential learning, on-the-job 
B Formal education and special course (degreed programs) 
C Professional activities, seminars 
D Individual readings 
E None of the above 
参考答案:A

QUEST Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management? 
A Classical / traditional 
B Pure project 
C Matrix 
D Project coordinator 
E None of the above 
参考答案:C