QUEST The project team form of organization confers both advantages and disadvantages.  Disadvantages of the project form include: 
A Conflict in authority between project manager and functional managers 
B Dual allegiance on part of team members 
C Complex prioritization of resources 
D Loss of developed procedures on project dissolution 
E All of the above 
参考答案:E

QUEST In general, groups will ____ the average individual problem solver on problems with multiple stages. 
A Perform better than 
B Perform worse than 
C Take less time than 
D Do about as well as 
E参考答案:
参考答案:A

QUEST Which of the following would most likely not be an essential objective of a project team kick-off meeting 
A Create a project technology master plan 
B Get team members to know one another 
C Identify project problem areas 
D Obtain individual and group commitments 
E Identify the project coordinator 
参考答案:A

QUEST In which type of organization is team building likely to be most difficult? 
A Functional 
B Projectized 
C Matrixed 
D Project expediter 
E Project coordinator 
参考答案:C

QUEST Management of a certain building was receiving complaints about slow elevator service.  The solution adopted was to add mirrors in the lobbies to reduce boredom while passengers waited.  This is an example of _____  . 
A Kepner-Tregoe method 
B Potential problem analysis 
C Decision analysis 
D Creative problem solving 
E None of the above 
参考答案:D